It is a document issued by the Municipal Engineering Office – Local Building Office to ensure safe occupancy and conforms to the provisions of P.D. 1096 also known as the “National Building Code of the Philippines” and its Implementing Rules and Regulations.
 

Office:

Municipal Engineering Office

Classification:

Indigenous Building – Simple

Standard Building Structure:

1-storey Building – Complex

2-storey Building and above – Highly Technical

Type of Transaction:

G2C – Government-to-Citizens, G2G – Government-to-Government. G2B – Government-to-Business

Who may avail:

Building, Electrical and Occupancy Permits Applicants

CHECKLIST OF REQUIREMENTS

WHERE TO SECURE

1. Building/Drawing Plans

Concerned Licensed & Registered Professionals

2. Detailed Cost Estimates

Concerned Licensed & Registered Professionals

3. Lot title and Tax Declaration

Municipal Assessor’s office

4. Other Certification (if applicable)

 

5. Barangay Clearance

Barangay Hall

6. Community Tax Certificate (CTC)

Municipal Treasury Office (MTO)

7. Fire Safety Permit

BFP

CLIENT STEPS

AGENCY ACTIONS

FEES TO BE PAID

PROCESSING TIME

PERSON RESPONSIBLE

1. Submit complete requirements and pay required fees

1.1. Receive the requirements and check their completeness

None

5 Minutes

Engineering Staff

MEO

1.2. Assess fees and prepare Order of Payment

Based on schedule of fees

10 minutes

Engineering Staff

MEO

2. Accompany inspectors during on-site inspection

2.1. Conduct evaluation of drawing plans and on-site inspection

None

4 hours (may vary depends on location)

Engineering Staff

MEO

 

2.2. Prepare and sign Permit

None

20 minutes

Engineering Staff

MEO

3. Receive the Approved Permit

3. Release the Approved Permit

None

5 minutes

Engineering Staff

MEO

TOTAL:

 

4 hours,

40 minutes

 